Tuesday, November 9, 2010

Walls ready for exterior insulation and siding.
Deck is waterproofed and ready for concrete topping

Rear elevation -ready for insulation and siding


Siding nearly complete on rear elevation.
Concrete deck topping compete.



Exterior insulation and strapping



Sprayfoam insulation complete at exterior basement walls.
Rimjoists, cantilevers and door /windows lintels were also sprayfoamed at the same time.

Interior insulation underway.

Boarders were hot on the heels of the insulation crew.